Cost Analysis of Brick Work



Brick Size:- 230×110×75(mm)
Bond :- English bond

: 8mm mortar use in brick work.

(Maximum 10mm mortar use in brick work)


= (230+(8))×(110+(8))×(75+(8))

= 238×118×83 (mm)

= 0.238×0.118×0.083 (mtr)

= 0.002330972 cub mtr

1 cub mtr Brick work:-

 Cub meter = 1/0.002330972

                     = 429 Bricks

1% wastage of bricks.

=429+6
=435 Bricks used in 1 cub meter Brick work.

Mortar used in 1cub mtr Brick work:-

Ratio of mortar:- 1:4

Required Cement in Brick work :- 1.5 bag

River sand :- 300kg or 0.200 cub mtr

Cost Analysis:-

(i) Brick = 435 bricks× 4.5rs
                = 1957.5 ~ 1958/-

(ii) Cement & River sand:-
   
      Cement = 1.5× 290
                     = 435/-

      Sand = 0.200× 700
                = 140/-

Total= 435+140
         = 575/-

(iii) Labour Charge:-

Mason- 1= 300/-
Beldar - 2= 150×2 =300/-

Total = 600/-

Total= i+ ii + iii

         = 1958 + 575 + 600

         = 3133/-