Cost Analysis of Brick Work
Brick Size:- 230×110×75(mm)
Bond :- English bond
: 8mm mortar use in brick work.
(Maximum 10mm mortar use in brick work)
= (230+(8))×(110+(8))×(75+(8))
= 238×118×83 (mm)
= 0.238×0.118×0.083 (mtr)
= 0.002330972 cub mtr
1 cub mtr Brick work:-
Cub meter = 1/0.002330972
= 429 Bricks
1% wastage of bricks.
=429+6
=435 Bricks used in 1 cub meter Brick work.
Mortar used in 1cub mtr Brick work:-
Ratio of mortar:- 1:4
Required Cement in Brick work :- 1.5 bag
River sand :- 300kg or 0.200 cub mtr
Cost Analysis:-
(i) Brick = 435 bricks× 4.5rs
= 1957.5 ~ 1958/-
(ii) Cement & River sand:-
Cement = 1.5× 290
= 435/-
Sand = 0.200× 700
= 140/-
Total= 435+140
= 575/-
(iii) Labour Charge:-
Mason- 1= 300/-
Beldar - 2= 150×2 =300/-
Total = 600/-
Total= i+ ii + iii
= 1958 + 575 + 600
= 3133/-